1. |
Ministry/Division |
|
Information and Technology Division |
|
2. |
Implementation Agency |
|
Bangladesh Hi-Tech Park Authority |
|
3. |
Name of the Project |
|
Basic Infrastructure for Hi-Tech City-2 Project. |
|
4. |
Implementation Period |
|
July 2019 - December 2022 |
|
5. |
Location of the Project |
|
Hi-Tech City, Kalikoir, Gazipur |
|
6. |
Approve Project Cost (in Lac) |
|
344.93 Crore |
|
7. |
Source of Fund |
|
GOB |
|
8. |
Date of the Approve |
|
ECNEC Approval date: 16 July, 2019, GO Issue: 25 September 2019 |
|
9. |
Main Objective of the Project |
|
A) Construction of basic infrastructures such as internal roads, land development, power, internet and gas connections, etc. for the purpose of building high-tech industries in the land of Bangabandhu Hi-Tech City-II at Kaliakoir. |
|
B) To attract local & foreign investment. |
|
|||
C) To create employment opportunities. |
|
|||
10. |
Main component of the Project |
|
Land development, Construction of service building from 2nd floor to 9th floor, Boundary Wall, 10 stored Dormitory building, Construction of Artistic Gate, Construction of Internal Bituminous Carpeting Road, Construction of compound drain, utility duct and footpath, Sub-station building, security protection for rail line side, STP, Gas connection, sewerage network, water distribution line, Landscaping, Lack development, Arborictulture, Ansar Barrack, Security post, Memorials / Mural, Box Culvart, Bridge (70mX20m), Bailey bridge/ foot bridge etc. |
|
(Service Building)
(Proposed masterplan)